Update about Footbridge

Shalford Station

There was a drop in session run by Network Rail to let people know when the footbridge would be replaced.

It will be put in place on the weekend of 9-10 December 2017 and then will be ready to use by 21st December.

The weekend work will close Shalford Station and parking will be restricted on Station Approach.

So far site preparations have involved removing the two remaining brick piers that supported the old bridge and two embankments are currently being prepared to receive new stones which will support the new bridge. Currently 80% of the ground works have been completed and the bridge is being fabricated ready to put in place 9-10 December.